- If there is a tie in Max. penalty, check where the Min. cost is less and give there.Min. cost in W2 = 36 (F2W2)Min. cost in F3 = 36 (F3W3)There is tie in Min. cost, too.If there is a tie also in Min. Cost, then you have to check
- What is the purpose of the Forward Pass in Critical Path Method (CPM)? - A) To calculate Early Start Time (EST)- B) To calculate Late Finish Time (LFT)- C) To calculate Early Finish Time (EFT)- D) To calculate Late Start Time (LST)
- What does the Backward Pass in Critical Path Method (CPM) calculate?- A) Early Start Time (EST) - B) Late Finish Time (LFT) - C) Early Finish Time (EFT) - D) Late Start Time (LST)
- n network analysis the network must have single starting point and a ____ ending point.a. Single b. Dual c. Multiple d. None of the above
- In Job Sequencing Problems, what is calculated to determine the optimal sequence?- A) Total processing time - B) Idle time- C) Elapsed time- D) Makespan
- What does the Modified Distribution (MODI) Method help determine in Transportation Problems?- A) Initial feasible solution- B) Optimal solution- C) Sensitivity analysis- D) Unbalanced assignments
- What is the purpose of the Critical Path Method (CPM)? - A) To allocate resources efficiently- B) To minimize project costs- C) To determine the longest path in a project network - D) To balance assignments
- Which method is used to find the optimal solution in Transportation Problems?A) (LCM) B) (NWCR) C) (VAM) D) Modified Distribution (MODI)
- What are the components of Linear Programming?- A) Decision Variables, Objective Function, Constraints - B) Analysis, Solution, Implementation- C) Assumptions, Formulation, Solution- D) Verification, Implementation, Evaluation
- Graphical method can be applied to solve a LPP when there are only__ variable.a. Four b. More than one c. Two d. Three
- What does the Free Float represent in Critical Path Method (CPM)?- A) Slack time available for an activity without delaying the project- B) Maximum time an activity can be delayed without delaying the project - C) Time required to complete the project- D) Total number of activities in the project
- In Transportation Problems, what is the purpose of the Least Cost Method (LCM)?- A) To allocate resources efficiently - B) To minimize transportation costs - C) To find the optimal solution- D) To balance assignments
- What are the types of Operations Research Models? - A) Deterministic and Stochastic - B) Linear and Non-linear - C) Qualitative and Quantitative- D) Static and Dynamic
- What is the objective of Theory of Games?- A) To maximize profits- B) To minimize costs- C) To analyze strategic interactions - D) To optimize resources
- What is calculated during the forward pass in Critical Path Method (CPM)?A) (EST) B) (LFT) C) (EFT) D) (LST)
- What are the phases of Operations Research?- A) Formulation, Solution, Verification, Implementation - B) Analysis, Solution, Implementation, Evaluation - C) Formulation, Solution, Implementation, Evaluation - D) Analysis, Solution, Verification, Implementation
- What does the Total Float represent in Critical Path Method (CPM)?A) Slack time available for an activity without delaying the project B) Maximum time an activity can be delayed without delaying the project C) Time required to complete the project D) Total number of activities in the project
- What criterion is used in Decision Theory to make decisions under uncertainty? - A) Laplace criterion- B) MaxiMin criterion- C) MiniMax criterion- D) Savage MiniMax regret criterion
- What does the North West Corner Rule help determine in Assignment Problems?A) Optimal solution B) Initial feasible solution C) Sensitivity analysis D) Unbalanced assignments
- What is the primary focus of Linear Programming?A) Solving algebraic equations B) Optimizing a linear objective function subject to linear constraints C) Analyzing nonlinear relationship D) Maximizing subjective preferences